Tip : What are the figures?
- Tap Pay in Navbar
- Pay >
{{Contracted Works Title}}
(in this example, Tokyo Ska Paradise Phase 3
)
- Pay >
{{Contracted Works Title}}
> Authorise or Verify
- Pay >
{{Contracted Works Title}}
> Authorise or Verify > Figure entry tile




Step 01
- Amount to Verify/Authorise (Gross) :
- This is the gross value of the contracted works from the relevant payment certificate.
- Retentions:
- This is any amount held back from payment in case of later defects (if retentions apply on this project).
- You must enter a value in every field, even if it is 0.
- Construction Industry Scheme (CIS) PAYE:
- This is any amount withheld for PAYE under the Construction Industry Scheme.
- Domestic Reverse Charge (DRC) VAT
- This is any amount withheld under the domestic reverse charge VAT scheme.
- When you have entered all the figures, the “Save draft” button will activate.
- Check that the figures you entered are correct, and hit “Save draft.” You will be returned to the Payments page, where you’ll see the state update.